COA tells DPWH to address delays in projects worth P96 billion
COA tells DPWH to address delays in projects worth P96 billion
Adrian Ayalin,
ABS-CBN News
Published Jul 07, 2023 01:29 PM PHT

MANILA — The Commission on Audit (COA) has told the Department of Public Works and Highways (DPWH) to address various reasons for project delays totaling P96.218 billion.
MANILA — The Commission on Audit (COA) has told the Department of Public Works and Highways (DPWH) to address various reasons for project delays totaling P96.218 billion.
In a 2022 report on the DPWH, state auditors noted that 2,395 locally-funded projects were delayed or non-implemented due to inadequate planning, detailed engineering, supervision and monitoring.
In a 2022 report on the DPWH, state auditors noted that 2,395 locally-funded projects were delayed or non-implemented due to inadequate planning, detailed engineering, supervision and monitoring.
Of the total, P60.077-billion projects were not completed within the specific contract time. Another P27.473 billion in projects were suspended, while P5.114 billion were either terminated or for termination.
Of the total, P60.077-billion projects were not completed within the specific contract time. Another P27.473 billion in projects were suspended, while P5.114 billion were either terminated or for termination.
The reasons cited for the delay included incomplete preliminary engineering studies, obstructions by electric and telecommunication poles, absence of construction workers and equipment, projects abandoned by the contractor, and natural calamities.
The reasons cited for the delay included incomplete preliminary engineering studies, obstructions by electric and telecommunication poles, absence of construction workers and equipment, projects abandoned by the contractor, and natural calamities.
ADVERTISEMENT
“Except for the COVID-19 pandemic and adverse weather conditions, the other identified causes of the delay in the implementation of infrastructure projects reflect the inadequacy of planning, supervision and monitoring of Management relative to the project implementation,” the auditors said.
“Except for the COVID-19 pandemic and adverse weather conditions, the other identified causes of the delay in the implementation of infrastructure projects reflect the inadequacy of planning, supervision and monitoring of Management relative to the project implementation,” the auditors said.
The audit report noted that the DPWH management agreed to the recommendations of the audit team to ensure full coordination with other government agencies such as local government units as well as private utility companies for more synchronized planning and implementation of the projects.
The audit report noted that the DPWH management agreed to the recommendations of the audit team to ensure full coordination with other government agencies such as local government units as well as private utility companies for more synchronized planning and implementation of the projects.
The audit team also said 653 infrastructure projects with a total contract cost of P20.718 billion were not executed in accordance with the provisions of the contract agreements, resulting in technical defects with a total cost of deficiencies of at least P369.172 million.
The audit team also said 653 infrastructure projects with a total contract cost of P20.718 billion were not executed in accordance with the provisions of the contract agreements, resulting in technical defects with a total cost of deficiencies of at least P369.172 million.
Among the defects noted by the audit team were major scaling and multiple cracks on concrete pavements in the Cordilleras.
Among the defects noted by the audit team were major scaling and multiple cracks on concrete pavements in the Cordilleras.
Other defects noted were those resulting from the use of inferior-quality materials.
Other defects noted were those resulting from the use of inferior-quality materials.
ADVERTISEMENT
Several cracks and potholes were also noted on the asphalt overlay on roads and retrofitting of bridges implemented by DPWH-Region V and the Sorsogon 1st District Engineering Office along Daang Maharlika from 2019 to 2021.
Several cracks and potholes were also noted on the asphalt overlay on roads and retrofitting of bridges implemented by DPWH-Region V and the Sorsogon 1st District Engineering Office along Daang Maharlika from 2019 to 2021.
“The foregoing technical defects and deficiencies may compromise the safety of public, cause further destruction on the infrastructures, and ultimately result in the wastage of government funds and resources if not immediately rectified/corrected,” the audit team said.
“The foregoing technical defects and deficiencies may compromise the safety of public, cause further destruction on the infrastructures, and ultimately result in the wastage of government funds and resources if not immediately rectified/corrected,” the audit team said.
The audit report however noted that the Sorsogon 1st DEO has agreed to conduct rectification and rehabilitation measures
The audit report however noted that the Sorsogon 1st DEO has agreed to conduct rectification and rehabilitation measures
DPWH Secretary Manuel Bonoan received a copy of the audit report on June 30, 2023.
DPWH Secretary Manuel Bonoan received a copy of the audit report on June 30, 2023.